We confirm that the Brixham Road Closure will be lifted by 6pm on 31st March as programmed.
The works are not yet fully complete. Snagging and landscape works will need to be completed from mid-April to mid-May, this will be under traffic management. In addition, the pedestrian crossing will be commissioned in May.
The S104 drainage to the south of the site will also be installed through April in the fields adjoining Brixham Road but these works will not affect the highway.
We have agreed with the local stakeholders to delay the next phase of works to Long Road and Windy Corner until later in the year. The timing of this work is to be agreed.